Neptune Atlas logo Neptune Atlas

Laytime

SHINC vs SHEX in laytime

SHINC means Sundays and holidays included: laytime (the time the charterer is allowed for loading or discharging) keeps counting through them. SHEX means Sundays and holidays excepted: those days do not count. The two terms can put a full day or more between two laytime calculations on the same port call. The extra letters that follow them, UU and EIU, decide what happens when cargo is worked on an excepted day anyway.

SHINC counts. SHEX stops.

The term changes when laytime runs out. It does not change how much laytime was allowed. A five day allowance is five days either way. Under SHEX those five days take longer on the calendar.

The terms side by side

None of these short forms is issued by any authority. The expansions below follow the Baltic Exchange glossary. The meanings follow the Laytime Definitions for Charter Parties 2013, a set of definitions agreed by BIMCO, CMI, FONASBA and the Baltic Exchange. Those definitions apply only when the charterparty (the charter contract) brings them in.

TermIn fullEffect on the count
SHINCSundays and holidays included Laytime runs every day, including Sundays and holidays.
SHEXSundays and holidays excepted (or excluded) Sundays and holidays do not count as laytime.
SSHEX or SATSHEXSaturdays, Sundays and holidays excepted The whole weekend and holidays do not count.
SSHINC or SATSHINCSaturdays, Sundays and holidays included Laytime runs every day. In effect the same as SHINC, said more loudly.
FHEX / FHINCFridays and holidays excepted / included The same two rules for ports where the weekly day of rest is Friday.
UUUnless used If cargo is worked in an excepted period, the time actually used counts.
EIUEven if used The excepted period stays out of the count even if cargo was worked in it.
ATDNSHINCAny time, day or night, Sundays and holidays included Laytime counts without a break once it has started.

What a bare SHEX means when the ship works on Sunday

This is the point most often argued, so it is worth reading the definitions closely.

Definition 19 of the Laytime Definitions 2013 says that excepted or excluded days "do not count as Laytime even if loading or discharging is carried out on them". So where those definitions apply, SHEX on its own already works like SHEX EIU. Work done on the Sunday is free time for the charterer.

Definition 22 gives the opposite rule, and only when the words are there. Unless used means that "if Laytime has commenced but loading or discharging is carried out during excepted periods, actual time used shall count as Laytime". Only the time actually used counts, not the whole day.

So the two letters work like this:

Some desks also write UUIWCATUTC, which the Baltic glossary expands as "unless used in which case actual time used to count". It says the same as UU and leaves less room for a claim that the whole day counts once work starts.

One timeline, six answers

Take one port call and change only the term. Laytime allowed is five days. Laytime starts on Thursday 8 October 2026 at 0800. Nothing else stops the clock. The question is when the five days run out.

Term in the fixtureWhat is exceptedLaytime expires
SHINCNothingTuesday 13 October, 0800
SHEX or SHEX EIUSunday 0000 to 2400Wednesday 14 October, 0800
SHEX UU, six hours worked on SundaySunday, less the six hours usedWednesday 14 October, 0200
FHEXFriday 0000 to 2400Wednesday 14 October, 0800
SSHEXSaturday 0000 to Sunday 2400Thursday 15 October, 0800
Written clause: Saturday 1200 to Monday 080044 hoursThursday 15 October, 0400

The first and last rows are 44 hours apart on the same ship at the same berth. If the ship completes on Wednesday evening, the SHINC charterer is on demurrage (the daily charge for delay) and the SSHEX charterer still has time in hand. You can run your own dates through the free laytime calculator, which takes the excepted time as an input.

The exception has edges, and the fixture must state them

The table above assumes a Sunday runs from midnight to midnight. Many fixtures do not. A common written form is Saturday noon, or Saturday 1700, to Monday 0800. That clause is not SHEX. It is a longer exception with its own hours, and the count follows the clause. The last row of the table shows the difference: 44 hours taken out instead of 24.

Three more edges are worth settling before the ship arrives:

After laytime runs out, the exceptions usually stop

SHEX protects the charterer only while laytime is still running. Definition 30 says demurrage "shall not be subject to exceptions which apply to Laytime unless specifically stated in the Charter Party". A Sunday that would have been excepted on day three counts in full once the ship is on demurrage. The rule is known as once on demurrage, always on demurrage. How to calculate laytime and demurrage works a full example where this happens.

The same Sundays also matter when the ship finishes early. Despatch (money the owner pays for time saved) can be counted on all time saved, which includes the excepted Sunday, or on working time saved, which leaves it out. Despatch vs demurrage prices both from one timeline.

Which term appears where

There is no rule, only habit, and habit differs by trade.

The statement of facts must show the working hours on each excepted day, or UU cannot be applied at all. The statement of facts explains what the agent should record.

This page explains how the terms are normally read. It is not legal advice. The charterparty in front of you decides the count.

References

Neptune Atlas

The Neptune Atlas laytime sheet keeps the exception as a field on each port, with its own start and end hours, so a Saturday noon to Monday 0800 clause is counted as written and a worked weekend under UU is put back by the minute. The free laytime calculator on this site does the same sum for one port, with no account. Every paid plan starts with 7 free days. A card is needed to start them, and cancelling before they end costs nothing.